Parallel

Parallel activity

This activity runs all the contained activities in the branches at once, without using conditions. All branches must complete for the workflow to continue. Drag and drop the activities you want to run in top-down order into each branch.

To set up this activity:

  1. Drag the activity from the toolbox pane and drop it in the Designer pane.
  2. In the properties pane, type a name and description of the activity.
    The name and description editors
  3. Drag and drop activities into each branch.

To add a branch, click the following Plus in the center of the activity:

This activity must contain at least two branches. To delete a branch:

  1. Select a branch in the designer pane to highlight it.
  2. Click the Delete Selected Activity button in the toolbar.

You may want to disable activities if you only want to test specific sections of your workflow. To disable activities:

  1. Select an activity in the designer pane to highlight it.
  2. In the Description property box, clear Enable.